|
HISTORY
OF MICHELL'S PASS
Its inaccessibility initially hampered the Bokkeveld’s progress. The first
farmers carried their necessities by pack animal through the kloof along the
river. From the waterfall it had to be carried over the mountain. Wagons later
reached Ceres via a detour of some 150 km over the Hex River Pass.
Bokkeveld
farmers also wanted to benefit from the great upsurge in the Cape market in the
18th century, and in 1765 Jan Mostert of the farm Wolvenkloof built the first
pass to Ceres. This pass was called Mostertshoek Pass and was certainly not
built for joyrides. It criss-crossed the river and was so steep under the
waterfall that the wagons had to be taken apart and carried over the mountain in
pieces. Mostershoek Pass was used until 1848.
From
1846 to 1848 Andrew Geddes Bain built a new road - a masterpiece for those days
- at a cost of 21 000 pounds. Small streams were forded with solid dry masonry
and living rock was hollowed out of the mountain slope. The pass was named after
Col. C Michell, Surveyor- General of the colony for 20 years.

This
great event laid the foundation for agricultural development in the Bokkeveld,
and with the discovery of gold and diamonds, the pass became an important route
to the gold and diamond fields. The transport industry started to blossom in
Ceres.
Goods
were brought from Ceres Station (now Wolseley) over the Michell’s Pass. A toll
house was later built on the pass, and the following tolls were levied: 3d per
wheel of four-wheeled vehicles without remschoens; 2d per wheel of other
vehicles; 1d per pack animal; ½d each for sheep, goats or pigs, and 2d each for
all other animals.
Bain’s
Michell’s Pass was used for nearly a century, until a concrete road was
completed on 31 March 1946.

THE
REBUILT PASS
Michell’s
Pass passes through the Ceres Nature Reserve and as its impact on nature had to
be limited, the rebuilt pass mainly follows the old route. The roadway was
widened from 6 m to 9.8 m and the hairpin bends were cut out. Three passing
lanes were constructed and the surfaced roadway is bordered with concrete paved
side drains and guardrails conforming to modern standards.
During
construction the pass was closed for traffic for three hours per working day to
accommodate blasting. All other construction work took place in full traffic
with a minimum of workspace available.
Some
400 000 m³ material was excavated from road cuttings, 180 000 m³ of which was used
for fills, the rest was crushed to be re-used as gravel layers. 250 000 m³ hard
rock had to be blasted, for which 83 000 kg explosives was used.
The
foundation of the new White Bridge consists of ten cylindrical caissons. Because
there are enormous boulders in the riverbed, this was the only viable option for
the bridge foundation. These caissons were excavated by hand to a maximum depth
of 13 m below the riverbed.
The
old toll house and parts of Bain’s original stone retaining walls were
preserved for posterity so that future generations can acknowledge Bain’s
engineering genius.
They
began to rebuild the pass in August 1988, and completed it four years later at a
cost of
R42 million.
 |